1. Material hoist loading
2. Installation of water, electricity, and air conditioning in the showroom
3. Secondary structure: 10th, 11th, 12th, and 13th floors + roof masonry
4. Secondary structure: wall grooving and pipe installation on the 6th, 7th, and 8th floors
5. Plastering on the 2nd floor; plastering on the 3rd floor; spraying and plastering on the 4th, 5th, and 6th floors; spraying and mesh installation on the 7th floor
Workforce:
- Water & electricity: 21 workers
- Secondary structure masonry: 12 workers
- Plastering: 36 workers
- Roof team (secondary structure): 6 workers
Progress:
- 11th floor supplementary masonry: 70% complete
- 12th floor supplementary masonry: 75% complete
- 13th floor masonry: 97% complete
- Roof masonry: 85% complete
- 3rd floor plastering: 97% complete
- 4th floor plastering: 35% complete
- 5th floor plastering: 25% complete
- 6th floor plastering: 30% complete
- 7th floor spraying and mesh installation: 20% complete